Proposed Gayford Facility

Rocky View County, Alberta

Proposed
Gayford
Facility

Armada Nowlit Energy proposes to install nine natural gas generator units to supply electricity to nine on-site data processing modules at the Gayford site in Rocky View County.

The project will be developed in accordance with applicable federal, provincial and Rocky View County requirements.

Conceptual oblique view of the proposed Gayford Facility with surrounding land and perimeter planting
Illustrative concept · July 2026 MSDP
18 MWProposed installed generating capacity
9 + 9Generator units + data processing modules
1.815 haSurveyed plant site · plus 0.091 ha access road
Project overview

Project location
and site use

The site is approximately 16 km southeast of Irricana and directly north of the existing Ember Resources natural gas compressor station. The balance of the parcel is expected to remain in agricultural use.

  • Legal locationNW ¼ Section 35, Township 26, Range 25, W4M
  • Road accessExisting approach from Range Road 252 and shared private access
  • Power useElectricity generated for on-site use; no grid connection or export proposed
  • OperationsRemote monitoring with scheduled inspection and maintenance visits
Local context map showing the proposed Gayford location north of the existing compressor station
Local context map. Source: MSDP, Figure 2. Select the image for a larger view.
Facility design

Proposed facility
configuration

The proposed layout places generator units, data processing modules, cooling equipment, emissions controls and electrical distribution within the surveyed plant site.

Power generation

6 × 1.9 MW
3 × 2.2 MW

Six generator units are rated at 1.9 MW and three at 2.2 MW, for a combined installed generating capacity of 18 MW.

Data processing

Nine data processing
modules

The nine modular containers house the data processing equipment. The generators would supply electricity for on-site use.

Engine cooling

Closed-loop
engine cooling

Engine coolant circulates through sealed piping and rejects heat through air-cooled radiators. The design does not include cooling towers. No groundwater will be consumed for engine cooling; the coolant will be delivered directly to site by the vendor.

Gas supply

Pipeline gas supply

Natural gas would be supplied through a pipeline tie-in, avoiding routine fuel deliveries by truck. The final connection and access arrangements will be addressed during detailed design and review.

Emissions controls

SCR emissions controls

The current design includes selective catalytic reduction (SCR) on all nine generators, together with predictive emissions monitoring.

Operating model

Remote operations

The facility would be monitored remotely and visited for inspection and maintenance. No permanent on-site staff are proposed.

Gayford concept site plan showing generator and data processing equipment north of the existing Ember facility
Concept site plan from MSDP Figure 7. Equipment labels and layout are conceptual and remain subject to detailed design.
Community considerations

Environmental and
community assessments

The MSDP summarizes independent assessments of noise and air quality, alongside water and traffic information for the proposed design.

Armada Nowlit Energy has retained independent professional firms for geotechnical, EE and ESA work. The results will inform detailed design and regulatory submissions.

Gayford third-party noise impact assessment summary: sound levels below the 40 dBA AUC Rule 012 nighttime limit at theoretical receptors within 1,500 metres.
Gayford third-party noise impact assessment summary from the linked Master Site Development Plan, sections 7.5 and 10.2. Select the image for a larger view.
01

Noise

An independent, licensed acoustic consultant assessed the proposed equipment and site layout. The MSDP reports that the Noise Impact Assessment found levels below the applicable AUC Rule 012 limits, using 40 dBA as the stated nighttime design criterion. Final equipment selections and operating conditions will be reviewed through permitting.

40 dBA · applicable nighttime criterion
02

Air quality

An independent, licensed air quality consultant modelled nitrogen dioxide concentrations, including background levels and emissions from the adjacent compressor station. The MSDP reports concentrations below the applicable Alberta Ambient Air Quality Objectives for the statistical measures assessed.

Modelled NO₂ · below applicable objectives
03

Water

No permanent municipal water or wastewater connection is proposed. Drinking water would be brought to site for construction and maintenance personnel, and a contractor would service portable sanitation facilities.

Transported drinking water · contractor-serviced sanitation
04

Traffic

Routine operations are expected to involve one to three inspection, maintenance or service visits per day. Construction traffic will follow approved access routes and road-use requirements.

Approximately 2–6 one-way vehicle trips per operating day
Noise impact assessment

Independent noise assessment

ACI Acoustical Consultants Inc. assessed the proposed equipment and site layout against AUC Rule 012. The July 2026 MSDP summarizes the findings.

Nighttime design criterion40 dBAStated in the MSDP for the assessed design
Assessment area1,500 mTheoretical receptors around the site
Assessment findingBelow limitAt all theoretical receptors assessed

The MSDP reports that no additional noise mitigation is required. Post-construction verification may be undertaken where required.

Source: Gayford MSDP, sections 7.5 and 10.2.

The landscape plan proposes native or drought-tolerant planting along the western and southern boundaries. Planting, shielded lighting and access controls are intended to reduce off-site effects while preserving emergency access and drainage.

Conceptual aerial rendering showing the Gayford Facility and proposed perimeter landscaping
Conceptual aerial rendering and proposed landscaping. MSDP Figure 12.

These renderings illustrate the current proposal; they are not construction drawings. Planting, equipment and layout details will be confirmed through permitting and detailed design.

Site management

Operations, safety
and reclamation

The MSDP describes measures for emergency response, operational monitoring and reclamation at the end of the facility’s operating life.

Emergency readiness

Emergency response planning

Before commissioning, the project plans to establish remote alarms, shutdown procedures, responder access and coordination with local emergency services.

Ongoing operation

Operational monitoring

The operating plan includes emissions controls, equipment monitoring, maintenance records and a process for responding to complaints.

Reclamation

Decommissioning and reclamation

At permanent closure, the plan is to remove equipment and associated infrastructure and reclaim disturbed land for agricultural use or tame pasture.

Approvals & next steps

Regulatory review
and permitting

The project will follow applicable federal, provincial and Rocky View County requirements. Construction and operation would begin only after the required planning decisions, permits and other authorizations are in place.

01 / REVIEW

Planning and regulatory review

Rocky View County land-use review and any applicable provincial or federal approvals.

02 / DESIGN

Detailed design and permitting

Confirm the site layout, drainage, road access, landscaping, lighting and emergency response arrangements.

03 / DELIVERY

Construction and commissioning

Construct in accordance with approved plans and complete required inspections and pre-operation checks.

Project documents

MSDP and
public notice

The July 2026 Master Site Development Plan (MSDP) describes the site, facility design, assessment findings and proposed mitigation. The community information meeting notice is shown below.

JULY 2026 · PDF · 40 PAGES

Master Site Development Plan

Gayford Data Processing Facility — prepared by VL Energy on behalf of Armada Nowlit Energy.

Read the MSDP ↗
Community information meeting

Community information meeting notice

Wednesday, October 28, 2026 · 6:00–8:00 p.m. · Keoma Community Hall, 112 6 St, Keoma, AB. Developer presentation at 6:15 p.m.

Gayford Facility public notice: community information meeting on October 28, 2026, 6:00–8:00 p.m., at Keoma Community Hall, with a developer presentation at 6:15 p.m.
Public notice for the October 28, 2026 community information meeting. Select the image to view it at full size.
Project enquiries

Contact the
project team

For questions about the proposed facility or the community information meeting, contact Armada Nowlit Energy.

Armada Nowlit EnergyGayford project enquiries

Project information and community enquiries

ANE.Info@Armada-Nowlit.COM